A M King will design and build a 72,142 ft2 dry warehouse expansion in Statesville, N.C., for Cheney Brothers Inc. (CBI). The project, which will provide an additional 7,000 pallet positions and a larger loading dock, is scheduled to be complete in spring 2022. It will bring the total square footage at the facility to 342,126.

In April 2019, A M King completed a 169,090 ft2 cold-storage expansion for CBI in Statesville, increasing the square footage at that facility to 265,000 ft2. The project included a penthouse refrigeration system zoned to support numerous temperature zones in the expansion area and conversion of a 37,388 ft2 existing cold-storage space to ambient temperature storage.

CBI currently handles more than 16,000 different products.